Switch Facility
Mobile Switching Center (MSC)
Midwest
Selective Site Consultants, Inc. (SSC) provided
many services in order to bring to reality a 22,000 sq. ft. switching
facility for a major wireless carrier. This facility was deemed
essential to the Client's network because of capacity constraints
and was mandated to be ready for switching equipment installation
and testing one year after the beginning of design.
Site Acquisition
SSC provided multiple property site candidates
that met narrow Client restrictions regarding proximity to existing
infrastructure and site buffering from hostile environments.
SSC aided in final site selection and throughout the contract
negotiations with landowners.
Zoning
SSC's zoning specialists guided the project
through the City's zoning procedures that included numerous hearings
and bureaucratic roadblocks. Amid public opposition, SSC was
successful in having the property rezoned from Residential to
BP-1 Planned Business Park that allowed the project to move forward.
As a requirement of the zoning process, SSC also facilitated
the replatting of the property, which involved negotiating a
County approval process.
Design
SSC managed multiple design subcontractors including
the architectural, electrical, mechanical, and security and fire
protection design firms and verified that all subcontractors
adhered to the Client's complex and continually evolving design
criteria. SSC completed the structural design in house. The design
of the project finished within the Client's timetable of supplying
finished design drawings and specifications for bid within four
months after design commencement.
Permitting
SSC negotiated the City permitting process and
successfully permitted the project in the face of difficult site
water drainage issues.
Bidding
SSC solicited contractor qualifications and
designated a list of qualified firms on a select bid list. An
RFP was developed by SSC and forwarded to select contractors.
Because of the compressed schedule, permitting ran concurrent
with the bidding process. In addition, during the bidding process,
Client specified design parameters were altered. SSC coordinated
the changes in the design and the addressing of City comments,
and kept contractors informed of changes using an addendum process.
SSC evaluated bids and provided a contractor recommendation to
the Client.
Construction Management
SSC managed the construction of the project
from start to finish. The Client's request that certain essential
rooms be completed early for installation of switch equipment
was successfully met, and equipment was brought on line within
schedule. Services provided include contractor management, shop
drawing review, evaluation of pay requests, evaluation of inspection
reports and punchlists.